Đường sắt đô thịHotline: 0825092007
Choose language▾

Twelve lessons

01

Build a map of which instruments applied when — and keep it current

As soon as the project is approved, build a table: each project milestone against the instruments in force at that moment. Add a row every time a new decree or circular replaces an old one. The table takes about two days to build and ten minutes to update. Without it, settlement means spending months reconstructing it from the memory of whoever is still there.

02

Lock the form of contract price in the bidding documents

One form of price per package. Where a package mixes several kinds of work, split the price annex by part. Most important: the way payment actually happens must match the form of price written down. This is the most expensive lesson here — most of the argument at verification sits precisely on this point.

03

Create records as the work happens, not at the end of the period

Acceptance records signed on the day of acceptance. As-built drawings prepared as soon as the item is finished. Site diary written daily. It sounds obvious, and it is the rule most often broken — and the direct cause of most amounts disallowed at settlement.

04

Photograph and measure what will be covered up, while it can still be seen

On a metro, underground work is a very large share of cost and cannot be measured again after completion. Reinforcement before the pour, tunnel support before the lining — each needs photographs carrying time and location, with a record signed by the parties. A photograph without time and location proves almost nothing.

05

Reconcile capital paid with the paying authority every year

The step most often skipped, and the one that finds the most differences. Do it annually, with a record signed by both sides. A difference found within the year can be dealt with; found after eight years it means tracing the whole chain of vouchers.

06

Get norms approved for specialised work before it is carried out

Machine tunnelling, signalling installation, overhead power, integrated testing — none of these appears in the general construction norm system. A new norm has to be prepared and approved before the work is done. Do the work first and seek approval later, and that cost will be suspended.

07

Decide the treatment of trial-running costs in advance

Before trial running starts, obtain approval of a document setting out the scope, the duration, the list of costs and the funding source. Open a separate tracking code in the accounts. It takes a week and saves months at settlement.

08

Allocate project management cost on a principle, not by feel

Cost directly attributable to an item goes wholly to that item; common cost is allocated in proportion to capital. Build the allocation schedule early and maintain it, rather than sitting down to divide it up at settlement — particularly where assets will go to several different receiving entities.

09

List the assets you expect to create, from the approval stage

Do not wait until handover to think about who receives what. Build the table early: item — asset type — expected receiving entity — legal basis for the transfer. It will be revised many times, but having it from the start makes every revision light.

10

Deal with inspection and State Audit findings at once, and keep the trail

A long, large project will almost certainly face at least one inspection or audit in its life. For each finding: keep the document, track each point in a schedule, record what was done about it and where the evidence sits. At settlement, this schedule is the first thing asked for.

11

Keep the people who know the file — and where you cannot, hand over on the record

A ten to fifteen year life is longer than the average tenure of a project officer. Every time the responsible officer changes, hand over against a document schedule, not in general terms. The document schedule belongs to the organisation, not to the individual.

12

Digitise early, and name files to one convention

Paper vouchers from the early years will fade, go missing, absorb damp. Scan and name them to a convention as they arise — package, document type, date, number. The cost of doing this is trivial beside the cost of hunting for a year-two acceptance record in year eleven.

Three costly misconceptions

Treating settlement as the accountant’s job

Settlement of investment capital is work for the whole project management unit: the technical department holds quantities and acceptance records, the contracts department holds the price terms, the planning department holds total investment, the accounts department holds the vouchers. Hand it wholly to accounting and accounting can only consolidate what it is given — and whatever is not given becomes a gap in the file.

Applying today’s instruments to work done years ago

A cost arising in 2022 is governed by what was in force in 2022, not by a 2026 instrument. A work item accepted in 2023 takes the norm in force in 2023. This is a basis error, and the verifying authority is entitled to reject it.

Invoking the special mechanism without proving it applies

The special mechanism shortens a number of steps — but only where the project falls within its scope and within its period of effect. The file must contain the proof: that the project is within the scope of NQ 188/2025, which part of the work arose after the resolution took effect, which step was shortened under which provision. A general reference to “the special mechanism” without citing a provision is not enough.

A checklist at five points

Not a compliance form. It is the short list of things that, if missing at that moment, cannot be recovered afterwards.

As soon as the project is approved

  • A map of which instruments applied when — built, with someone named to keep it current
  • Which of the four legal tracks the project sits in, with the document proving it
  • A schedule of total investment by period — opened even before any adjustment
  • The list of assets expected to be created and their expected receiving entities
  • A file naming convention and electronic folder structure — issued in writing

Before issuing the bidding documents for each package

  • The form of contract price settled, one form per part of the work
  • Bidders required to submit a price analysis and a base bill of quantities as contract annexes
  • A technology transfer schedule with acceptance criteria and the value attached to each item
  • Training obligations tied to acceptance milestones, not paid as a lump sum in advance
  • Contract language, responsibility for translation, and the conversion rate for foreign contractors

Throughout construction

  • A site handover register by chainage and by date, signed by three parties
  • Norms for specialised work approved before the work is carried out
  • Photographs and measurements of what will be covered up — with time, location and a record
  • Annual reconciliation of capital paid with the paying authority
  • Allocation schedules for project management and consultancy cost — updated regularly
  • Every extension of time recorded in a contract addendum, not in correspondence

Before trial running

  • A document approving the scope, duration, cost list and funding source
  • A separate tracking code for trial-running cost in the accounting system
  • System safety assessment and certification — with its own estimate and its own contract
  • As-built records for the equipment, with a Vietnamese version

Before handover

  • The list and value of assets to be handed over, by receiving entity
  • Assets classified as long-term or short-term
  • The project management unit’s own assets: ledger reconciled to physical count, residual value established
  • Surplus materials and equipment: ledger reconciled to physical count, with a disposal plan
  • Receivables and payables attributed to the correct parties, with recommended treatment

Applying this to your own project

If you would like these turned into procedures and forms for your unit, that is one of the services we provide — see settlement records management from day one.